July 3, 2014

Banish long Sprint Planning meetings

by Sampath Prahalad

In the Agile world, a Sprint Planning meeting would typically have the Business / Product Owner listing and explaining each story to be delivered and the team goes about doing their best to understand each story based on questions and discussions. The team then estimate the effort needed for each story and commit to whatever they think is feasible within the Sprint duration. For a 2 week Sprint, this typically takes around 3-4 hours.

In many cases, discussions on stories unearth scenarios that need further Analysis by the Product Owner before they can be ready for development. These stories cannot be picked up for development even if they are of highest priority since there are some unknowns about them. This means that the Sprint backlog could consist of stories that are not of highest priority. Also, this results in a long Planning meeting due to more discussions and more stories to discuss.

Is there a way to change this and ensure that the Sprint backlog is filled with stories of highest priority and value? Also, is it possible to have a shorter planning meeting?

Fortunately, the answer is Yes…

The key is to remove the discussions and visit all possible scenarios up front.

The answer is to have an Elaboration session for the next Sprint in the middle of the current Sprint. The Scrum Master gets the team and the Product Owner together for the Elaboration session. Here, the Product Owner presents the stories for development in the next Sprint and solicits questions and feedback. The team and Product owner discuss all possible scenarios and get a complete understanding. There is a huge possibility that some stories might not be ready for development. The Product Owner then has the time to action these before the actual Sprint planning meeting a week later.

This way, the team is fully aware of the stories coming up in the next Planning meeting, the Product owner has time to fine tune his high priority stories and many stories can be committed to and taken up for development without much discussion at the planning meeting. All this leads to a short planning meeting and a less stressed out team. The additional meeting that is added would provide value by unearthing issues up front thus providing enough time for resolution.

I strongly encourage management and teams to try this option out. Do let us know how this worked for you.

February 14, 2013

Definition of Ready for Sprint Planning meetings

by Sampath Prahalad

Nice video on How to improve Sprint planning.

One of the tips given is to have a Definition of Ready.
Only those user stories that are ready to be presented are discussed in the Sprint planning meeting. This ensures that the Product Manager does his home work on the user stories to be taken up in the Sprint. This also reduces the time taken for the Sprint planning meeting.

See the video below for some good tips.

 

November 29, 2012

Documentation updates in Scrum projects

by Sampath Prahalad

Scrum and other flavors of Agile expect a potentially shippable product at the end of each Iteration or Sprint. This typically means that each user story within the Sprint has to be developed, integrated, tested, documented and made deployable to production. While this is not new, I have seen many variations to this in my experience with Agile teams. I am going to deal now only with the Release documentation part here. Everything else is out of scope for now.

Consider the scenario below. In a reasonably small organization, we have the Product Marketing manager Laura who doubles up as Product manager of a desktop application GoldSpot that back-ends with a database server. Laura is responsible for pretty much everything on GoldSpot. She is always seen juggling and shuffling between business case evaluation, wire-framing, product backlog creation and constant prioritization, user acceptance testing, creation and updates to user and admin documentation, customer demos, marketing communication, etc. The product development team consists of 3 developers, 2 test engineers and a Scrum master. The team and Laura meet over Skype for the Sprint planning meeting, the daily stand-ups, Sprint review and retrospectives. The team is in their third Sprint, have just created a prototype worth showing to customers and have 3 more Sprints to go in this Release.

read more »